Freeway Performance Initiative - TOS and Ramp Metering Elements

Description: In Fremont, from 0.4 mile south of Auto Mall Parkway to 0.1 mile north of Mission Boulevard (Route 238). Install ramp metering and various Traffic Operations System (TOS) elements.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Fremont
Zip Code
 
Senate District
10
Assembly District 25
Congressional District 17
 
Caltrans District
04, 07
 
 
County/State Route Alameda 680
Postmile Begin/End 3.6 6.5
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  1112.00      
Lane Miles Added (HOV)      0.35  
Lane Miles Added (Mixed)      0.36  
Peak Period Time Savings (minutes)  11481      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Emily Landin-Lowe (510)286-5124   emily_landin-lowe@dot.ca.gov
Design (PS&E) Phase
Caltrans Emily Landin-Lowe (510)286-5124   emily_landin-lowe@dot.ca.gov
Right of Way Phase
Caltrans Emily Landin-Lowe (510)286-5124   emily_landin-lowe@dot.ca.gov
Construction Phase
Caltrans Emily Landin-Lowe (510)286-5124   emily_landin-lowe@dot.ca.gov
 
Corridor System Management Plan
Caltrans Emily Landin-Lowe (510)286-5124   emily_landin-lowe@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$7,000 $-1,260 $5,740
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$2,120 $0 $2,120
Non Budgeted ETC
$0 $0 $0
 
Total**** $9,120 $-1,260 $7,860

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,400 $0 $1,400 $0
Design(PS&E)
$700 $0 $700 $33
Right of Way
$20 $0 $20 $1
Construction
$7,000 $-1,260 $5,740 $5,738
 
Total* $9,120 $-1,260 $7,860 $5,772

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2011 

04/01/2012 
 

 
07/01/2011 

04/30/2012 
100  07/01/2011 

04/30/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

06/01/2012 
 

 
 

06/01/2012 
100   

06/22/2012 


-1 
Begin Right of Way Phase

End Right of Way Phase
 

06/01/2012 
 

 
 

06/01/2012 
100   

01/08/2015 


-32 
Begin Construction Phase

End Construction Phase
11/01/2012 

11/01/2012 
 

 
11/01/2012 

11/01/2014 
100  11/16/2012 

06/27/2013 


16 
Begin Closeout Phase

End Closeout Phase
12/01/2014 

12/01/2015 
 

 
12/01/2014 

12/01/2015 
100  06/28/2013 

07/21/2015 
17 

Corridor System Management Plan
Adoption Date        
Implementation Date        
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 1112.00
Lane Miles Added (HOV) 0.35
Lane Miles Added (Mixed) 0.36
Peak Period Time Savings (minutes) 11481

Bond Funding Cost
Adopted:
$7,000,000
Current Approved:
$6,673,000
Actual Expenditures:
$5,738,000

 

Status as of December 31, 2023.